Owner | CONFIDENTIAL |
Client | CONFIDENTIAL |
Location | Saudi Arabia |
Project Description
Sour Water Stripper, Meg Regeneration, Condensate Treatment, Rich Meg, Lean/Fresh Meg Storage and inter connecting pipe rack 6 & 7, Part of marajan increment program, Packages 9.
Scope of Work
No of Equipment’s SWS - 30 , MEG – 52, Rich MEG storage-10, Condensate Treatment-38, Lean/Fresh MEG storage - 19 nos . Total Equipment’s – 149 nos
PIPING:
Big Bore Lines in SWS 420 + Small Bore 150 piping lines with about 1150 isometrics.
Big Bore Lines in MEG 730 + Small Bore 260 piping lines with about 2050 isometrics.
Big Bore Lines in Condensate Treatment 560 + Small Bore 200 piping lines with about 1700 isometrics.
Big Bore Lines in Rich MEG storage 150 + Small Bore 60 piping lines with about 450 isometrics.
Big Bore Lines in Lean/Fresh storage 285 + Small Bore 115 piping lines with about 860 isometrics.
Total Big B ore lines 2300 + Small Bore 885 piping lines with about 7060 Isometrics.
CIVIL :
Total no of Equipment foundations designed by CIVIL 149 nos.
Total no of main unit pipe racks designed by CIVIL – 09 nos