Lone Star NGL Fractionators Mariner South Project
 

M/s ETP is setting up a fractionation unit north of the Fractionation Train 2 which will process 100,000 BPD of HD5 Feed containing approximately 90.4% Propane, 7% Ethane and 2.6% Iso-butane by liquid volume percent and produce a Propane export product containing approximately 95.6% Propane, 1.75% Ethane and 2.65% Iso-butane. The location of this unit is Mont Belvieu.

S&B is awarded with this contract and VEC is supporting S&B in performing detailed engineering services involving multi discipline like Process, Civil & Structural, Piping, Stress, Mechanical, Instrumentation and Electrical.

Job awarded: May’13

The target Mechanical Completion date is October 5, 2013